GWH300-20MW

Goldwind Science & Technology Co., Ltd. · 金风科技

Offshore In production 20 MW class
20 MW
Rated power
300 m
Rotor diameter
70,686 m²
Swept area
283 W/m²
Specific power

Specification

Rotor & rating

Rated power
20 MW
Rotor diameter
300 m
Swept area
70,686 m² (calculated from rotor diameter)
Specific power
283 W/m²
Blade length
147 m

Wind conditions

Cut-in wind speed
—
Rated wind speed
—
Cut-out wind speed
—
IEC class
—

Drive train & tower

Drive train
Medium speed
Generator
—
Tower
—

Commercial

Status
In production
Segment
Offshore
First installation
2026
Markets
China
Certifications
—

Largest Goldwind offshore platform, marketed as GWH300-20(25)MW: 20-25 MW, 300 m rotor, 50-70 m water depth, designed to ride out super typhoons above 60 m/s. First unit - a 20 MW machine with 147 m blades and a 174 m hub - was installed at CTG Zhangpu Liuao Phase 2 (Fujian) in January 2026 and grid-connected on 5 February 2026, reported as the world's first 20 MW turbine connected offshore, with expected annual output above 80 GWh. A 22 MW nacelle for the same platform rolled off the Shantou production line in December 2024.

Other Goldwind Science & Technology Co., Ltd. models

Sources for this specification

  1. [1]“offshoreWIND.biz - Goldwind starts producing components for 22 MW offshore wind turbine with 300-metre rotor (2024-12-31),” offshorewind.biz. Accessed: Nov. 18, 2026. [Online]. Available: https://www.offshorewind.biz/2024/12/31/goldwind-starts-producing-components-for-22-mw-offshore-wind-turbine-300-metre-rotor
  2. [2]“offshoreWIND.biz - China Three Gorges grid-connects world's first 20 MW wind turbine installed offshore (2026-02-06),” offshorewind.biz. Accessed: Nov. 18, 2026. [Online]. Available: https://www.offshorewind.biz/2026/02/06/china-three-gorges-grid-connects-worlds-first-20-mw-wind-turbine-installed-offshore
  3. [3]“回归本质,聚焦价值——金风科技发布全新一代海陆旗舰产品 (Goldwind launches new-generation onshore/offshore flagship products),” goldwind.com. Accessed: Nov. 18, 2026. [Online]. Available: https://www.goldwind.com/cn/news/focus-1038084705804846080/ OEM document
  4. [4]“金风科技20MW海上风电机组成功吊装,刷新全球纪录 (20 MW offshore unit installed, world record),” goldwind.com. Accessed: Nov. 18, 2026. [Online]. Available: https://www.goldwind.com/cn/news/focus-1197933244742555648/ OEM document

Compiled 2026-11-19. Specifications change without notice — confirm against the manufacturer's current datasheet before tendering.