EW8.5-230
Shanghai Electric Wind Power Group Co., Ltd. (SEwind) · 上海电气风电
Specification
Rotor & rating
- Rated power
- 8.5 MW
- Rotor diameter
- 230 m
- Swept area
- 41,548 m²
- Specific power
- 205 W/m²
- Blade length
- —
Wind conditions
- Cut-in wind speed
- —
- Rated wind speed
- —
- Cut-out wind speed
- —
- IEC class
- —
Drive train & tower
- Drive train
- Medium speed
- Generator
- —
- Tower
- —
Commercial
- Status
- In production
- Segment
- Offshore
- First installation
- 2022
- Markets
- China
- Certifications
- —
The first unit of SEwind's second-generation Poseidon platform, hoisted on 8 September 2022 at Shandong Energy Group's Bozhong offshore site B with what was then the largest rotor ever erected, 230 m. Semi-direct-drive offshore machine for low and medium wind speed sites; at a 7.5 m/s annual mean it yields about 28 GWh a year, and its 41,548 m2 swept area equates to roughly 5.8 standard football pitches at a specific power of 205 W/m2. This is the offshore workhorse behind SEwind's 2022-2025 Chinese offshore deliveries, and its 8.5 MW/230 m pairing remains the reference point for China's mid-wind offshore segment.
Other Shanghai Electric Wind Power Group Co., Ltd. (SEwind) models
Sources for this specification
- [1]“海神平台 EW8.5-230 首台机组吊装 (上海电气数字杂志, 2022),” dmg.shanghai-electric.com. Accessed: Nov. 18, 2026. [Online]. Available: https://dmg.shanghai-electric.com/shem/appnews/135/4319/6217-1.shtml OEM document
- [2]“Shanghai Electric EW8.5-230 — turbine sheet (The Wind Power database),” thewindpower.net. Accessed: Nov. 18, 2026. [Online]. Available: https://www.thewindpower.net/turbine_en_1904_ew8.5-230.php
- [3]“海神平台EW8.5-230 EW12.X-252 EW14.0-263 EW16.0-252 EW18.0-263,” shanghai-electric.com. Accessed: Nov. 18, 2026. [Online]. Available: https://www.shanghai-electric.com/group/c/2018-12-20/573714.shtml OEM document
Compiled 2026-11-19. Specifications change without notice — confirm against the manufacturer's current datasheet before tendering.